The start of the finishing of the room


We got a lot done this week!  I am really proud of our work and meeting our deadline of having the house ready to host a mother's day dinner for 13 people.


Crown Moulding
Damn you, angles gamma and alpha!
There is math here that we had no idea how to deal with, goodness gracious.  The math gymnastics stem from from the fact that the angles between the wall and ceiling and the moulding are not 45 degrees.  Our angles were 58 and 32 degrees, which required strange saw adjustments in order to allow us to lay the moulding flat on the saw's table surface for the cuts.  We have a fantastic power mitre saw that is capable of also bevel cuts.  For a mitre cut, you adjust the blade relative to the vertical fence of the saw.  For a bevel cut the blade is adjusted relative to the horizontal table of the saw.  Based on math that wasn't obvious to us, we needed a bevel of 33.9 degrees and a mitre 31.6 degrees.  It took us a while to get the first board properly cut, and a few practice cuts.  Then begun the challenge of nailing through the moulding into the ceiling joists and the wall studs.  After putting up a few nails to hold it in place, we let go of the moulding and stepped back to admire our work.  The moulding promptly fell off and we promptly got into the car to go rent a finish nailer.

Matt went into Home Depot to get the supplies and I stayed in the car with Molly.  This is when he got the demo of how to avoid nailing our hands to the ceiling, and an idea of how loud this thing is.  He was clever in setting me up to fire the gun for the first time, and recording the result.  It's loud, and a little scary to fire.  Once the matter of securing the moulding was handled, we went back to figuring out the angles.  After messing up a few more cuts, we decided to use a cheater method of simply holding the moulding against the saw's table and fence the same way it would be oriented relative to the ceiling and wall respectively.  This allowed us to have just a 45 degree mitre and zero bevel, muuuuuch easier.  We finished the moulding up that late night and were pretty happy, until we opened the back door to bring Molly inside.

Matt called for her and we turned all of the lights on outside to find that our backyard was dog-less.  Further complicating the matter is the fact that our street has buried electrical lines, so no street lamps.  Being calm under pressure, I bolted out the front door honking a squeaker tennis ball, crying and yelling for Molly.  Matt, who smartly took a flashlight, found her in our neighbors yard who's property backs up to ours.  She was panting and happy and had no idea why we were so lathered up, after all she had a fun romp through the neighborhood.  We've since reinforced the area of the fence she got through.

The start of the end
What would a project be without
all of our tools to trip over?
Hello, Orange!
Because we're not professionals, some areas of the crown moulding needed some serious caulk.  There was only one seam that wasn't in a corner which made our lives a little easier.  We did two coats of ceiling paint on the ceiling and crown moulding, then it was time for color!


We are so happy with the color, its exactly what we wanted.  We're ordering the tile today or tomorrow and shrewdly using a competitors coupon to get 20% off our order which is a huge help.  We'll have a tiling party once we get all the supplies, let us know if you'd like to join us for a day of rolling around on the floor (we'll even feed you).  Amateurs welcome because it will be the blind leading the blind.

Exhibit A: a happy painter


Quick screen solution
Magnets to be sewn along bottom,
sides and middle seam.
This is how Molly relaxes after
a hard day's work.
I have run through a few screen doors, as has my brother, as have our dogs.  I didn't want to have screen doors on the french doors between the Pit and the pool deck.  Two of these weighted screens seemed like the best option.  They secure with velcro, but we plan on upgrading this by sewing some of those fantastic rare earth magnets (how do they work?) in key places.  Molly is fine going through them, but has been trained to wait for us at open doors.  So even when the french door is open, we still have to give her the go-ahead to exit.  This doesn't stop her from running back through them into the house immediately after a quick dip in the pool.


Mother's Day
We finished touching up the paint job at 11:00 on Sunday morning then started a flurry of cleaning to prepare for a Mother's day dinner.  We had 11 people over: parents, siblings and spouses and aunts.  Our guests graciously helped us by bringing sides and desserts which was huge because we are still oven-less (hopefully by the 16th, fingers crossed).  We made herbed pork tenderloin on the grill and a rhubarb currant chutney, cucumber salad and a regular salad.  Also on the menu was appetizers, mashed potatoes, citrus rice with carrots and candied walnuts, ravioli salad with pine nuts, tomatoes and olives, rice pilaf, and pound cake with strawberries and whipped cream.  If I forgot your contribution, I apologize.

My brother John and cousin Dave came over a little early to take a maiden dip (voyage?) into the still frigid pool.  David recorded the temperature on the digital  thermometer at 66.6, fitting to say the least.  Molly joined them in the water, as did our mother's dog Olive, or Violet as only my brother calls her.  Olive didn't really seem to enjoy the water too much, her coat is incredibly heavy when wet so she probably couldn't swim too easily.  Matt hopped in too, but I still think it needs another 5 or 15 degrees to be an appropriate temperature.

Matt and I had a great time, it makes us really happy to have a house full of people we love and feed them good food.  After all, isn't it great to eat with friends?

Sunday, May 6, 2012

It's definitely getting better

An update on our continuing drywall saga
Thank goodness for goggles
and respirators!
We completed our last coat of joint compound and a final round of sanding.  I am not sure a professional would call it "done" but someone riding by on a horse wouldn't notice our errors.  In consulting my brother, John, for advice he gave me sage advice: "if your gonna do it you may as well do it right."  I laughed really hard when I read this.  We're not trying to do this poorly, but it certainly does seem like amateur hour around here sometimes.  For our next drywalling adventure, I would much rather hire out the work than spend forever and a day dealing with.  To prep for the next step, we threw some primer on the fresh drywall and mud.


Yeah, we have had asbestos...what's it to ya?
Halley, stayin' alive
I packaged up some tile samples from the Pit and laundry room to have the tile and adhesive tested for asbestos.  The tiles were non-friable 10% chrysotile, the most common form of asbestos.  I started panicking, Matt remained calm and started research on the interwebs.  If you're going to have asbestos in your house, vinyl asbestos tile (VAT) is the form you wish for.  It is certainly something to be careful with, but the removal process was not too difficult.  I phoned the Bucks County PA Dept. of Environmental Protection and he put my fears at ease.  Homeowners are able to remove their own VAT (no permit required) and it can be incorporated into the regular waste stream.
Matt, being a sad panda

Prepping the room
We prepped the room by emptying it completely and taping ourselves into in with with plastic sheeting.  The vents and outlets were all taped up and the HVAC system was turned off.  To keep the asbestos off of us we used goggles, respirators with cartridges rated for asbestos, gloves, tyvek coveralls and of course, booties.  Once all the prep work was taken care of, the removal process was quite simple.  We sprayed the area we were working on with "amended" water (which just mean there's a bunch of dish soap in it)  and then used putty knives to pry under the tiles and pop them off.  We had an interesting surprise concerning the strange wall bump-out that required the stupid drywall operation.  For some reason, this wall bump-out was built (perhaps at all?) on top of the tiles.  The tiles were bagged, bagged again and sealed.  Before we opened up the containment zone we collected all the debris from the floor, wiped down all the surfaces and mopped.  When we were ready to break the seal, we ran outside and ripped our masks off to get fresh air.  From start to finish the process took about 3.5 hours.  Glad to be done with that mess.  At some point we'll tackle the laundry room/powder room and perform the same operation there, so after that we'll really not have any asbestos.
The dirt line represents the edge of the
bumped-out drywall...previous home owners
were real dingbats
Molly, trying to get through 2 layers
of plastic....to help?




















Dancing about, post asbestos removal and post
shower, I think "Bare Necessities" from Jungle
Book is playing in my head for some reason.  Molly
is happy to join us on the other side of the plastic
Moving forward
We've finished our first all-over coat of oil-based primer.  After some research I found that using an oil-based primer will prevent the underlying layer of wallpaper from peeling off the walls.  Once this has encapsulated the awful wallpaper, we can pressed on with spackling and sanding the wallpaper seams.  We are hosting Mother's Day for both out families next Sunday, so there are a few key steps to get finished:

  • Sand the wallpaper seams
  • Another coat of oil-based primer all over the place
  • Ceiling paint, on the ceiling
  • Paint the walls
  • Put up crown moulding
  • Pour the self leveling concrete
It crossed our minds to try to get the tiling done before then...but with two full time jobs it isn't going to happen.  We should also try to make a larger dent in our unpacking.  This was a hard week (see Matt's post) but we really got a lot done over the weekend.  Slow, but steady, progress.

Tuesday, April 10, 2012

Ch ch ch changes! (Sing it like David Bowie)

So today we started renovating the room we've been calling "the pit."  It is an informal living room that is a step and a half lower than the rest of the first story because it's been built directly on concrete slab.  It has wide openings to the kitchen towards the rear of the house and to the foyer in the front of the house.  On this level there is also a dumb little office and a coat closet.  All these rooms feature wallpaper on the walls and ceiling, yes even in the closet!  Our game plan is to remove the wall separating the main room from a dumb office.  Here is the starting point:









I will take this time to point out we ran a carpet cleaner over this nonsense twice and the absurd skid marks from years of recliner use are permanent.  And don't judge our mess, we're just trying to spread all of our belongings from the ~680 sq.ft. apartment to the ~2,400 sq.ft. house.

We did a lot of climbing around  in the attic and himming and hawing about whether the dividing wall was load bearing or not.  Matt is trying to get me to pay attention to some detail about the ceiling joists, I am slacking.


The drywall removal began and went pretty quickly.  We used the sawzall (favorite tool by far) to split the studs which weren't even actual 2x4's and Matt used his mass to pry the footer off of the nails that were in the concrete slab.


Done for the night!


There is a slight difference in the ceiling height and wall depth in the office vs the main room.  I think we'll handle this by adding some wooden strips to the ceiling/walls to support a new layer of drywall that will be level with the rest of the room.  We can't think of another way to handle this properly or hide it decoratively so comments are welcome!  Hopefully more to follow soon, assuming we're not too beat.